With the hotel organising a two week shut down for renovation works, they decided to upgrade their plant room.
Acting as principle designer we initially undertook a R & D survey which highlighted areas of asbestos, Ipswich Insulations where tasked with the safe removal. Following the client accepting our design, we were tasked with completing the strip out works and the installation of a new plant room, with two AIC Nesta boilers tasked with providing heat for three AIC Silox tank-in-tank cylinders, and the existing heating system, with our system being protected by a PHX.
As part of this project we installed a new suitably sized gas main, new plant room ventilation and new flues rising through an existing chimney.
Although the deadline was extremely tight, through long hours and teamwork, we managed to deliver the project.